Project Update - October 2019

Geelong Waterfront Third perspective V5 (1).jpg

On-Water Construction Activities - October 2019

- Set up and establishment of the temporary construction compound at Limeburner’s Point.

- Continued off site fabrication of the precast wave attenuator units and floating marina.